In 2025, the market is valued at USD 820.00 million and is forecast to grow at a CAGR of 14.0%, reaching USD 3.03 billion by 2035. Growth is driven by neocloud leases signed in 2026, the national artificial intelligence plan approved in June 2026 and Nvidia's expanding Israeli footprint.
Market Overview
The Israel hyperscale data center market has moved from a handful of colocation halls to a contest for grid capacity. Cloud regions, graphics processor clusters and defence workloads are all seeking power in a country with a small, isolated electricity system.
Three forces are shaping the market: lease-backed artificial intelligence demand, with Nebius and Crusoe signing for well over 100 MW in 2026; grid scarcity, as connection requests reached about 27,000 MW against average national consumption of roughly 9,000 MW; and a regulatory reset that now caps each new campus.
In July 2026 the Electricity Authority froze new applications for 140 days, and in October 2026 it outlined a 200 MW cap per new data center. Developers must also post financial guarantees of NIS 2 million per requested megawatt.
Key Market Trends and Insights
- Grid queue overwhelms supply: Noga received about 19,000 MW of new data center requests within two months to July 2026, on top of an existing backlog of about 8,000 MW.
- Regulated cap on campus size: The Electricity Authority outlined a 200 MW ceiling per new facility in October 2026, with an extra 1,000 MW released for large projects and 300 MW kept for government use.
- Neocloud leases anchor demand: Mega DC contracted 80 MW to Nebius in January 2026 in a deal estimated at USD 880 million, with delivery between the third quarter of 2026 and the first quarter of 2027.
- Large capital commitments: Crusoe announced about USD 10 billion of Israeli investment in June 2026, including 67.6 MW leased from Mega DC and 40 MW at Afula.
Value is moving from compact colocation halls towards large campuses leased to cloud providers, artificial intelligence developers and public bodies. Electrical infrastructure leads in growth because substations, backup power and grid connections decide who can build, while mechanical and cooling spending rises with rack density. Underground and fortified halls keep a premium for resilience, yet power-integrated campuses beside gas plants advance fastest as developers seek dedicated supply. Cloud providers and hyperscalers remain the largest customers, and artificial intelligence and graphics processor cloud operators grow quickest. Tel Aviv and the Central District stay largest on connectivity, while the Southern District gains share as land and power projects cluster in the Negev. Regulatory caps and guarantees favour well-funded operators and will reshape how capacity is allocated.
Key Metrics
- Market Size 2025: USD 820.00 million
- Projected Market Size 2035: USD 3.03 billion
- CAGR 2026 to 2035: 14.0%
- Fastest-Growing Component: Electrical Infrastructure: 15.8% CAGR
- Fastest-Growing Facility Type: Power-Integrated Campuses: 17.2% CAGR
- Largest Revenue Segment 2025: Cloud Service Providers and Hyperscalers
- Dominant Region: Tel Aviv and Central District
- Highest CAGR by Region: Southern District: 17.6%
- Pending data center grid requests, July 2026: About 27,000 MW
- Base Market Amount 2025: USD 820.00 million
Lease-Backed Artificial Intelligence Demand Drives Expansion
Revenue is on course to expand more than threefold, from USD 820.00 million in 2025 to USD 3.03 billion in 2035 at a 14.0% CAGR. Long leases signed with Nebius in January 2026 and Crusoe in April and June 2026 give builders contracted revenue before the first rack is installed.
Power Equipment and Gas-Linked Campuses Lead Growth
Cloud providers and hyperscalers hold the largest share, but Electrical Infrastructure grows at an estimated 15.8% CAGR and Power-Integrated Campuses at an estimated 17.2% through 2035. Dalia Energy raised its stake in a planned 250 MW Ashdod campus to 50% in August 2026, designed around a neighbouring gas plant.
Regulation Now Decides Who Builds
The Electricity Authority froze new grid applications for 140 days from 20 July 2026 and in October 2026 outlined a framework that rations scarce megawatts and screens out speculative projects.
- Each new data center is capped at 200 MW of consumption
- Guarantees of NIS 2 million per requested megawatt deter queue-squatting
- Facilities must be able to disconnect during extreme grid load
- Base Year: 2025
- Historical Period: 2019 to 2025
- Forecast Period: 2026 to 2035
- Market Size 2025 (USD million): 820.00
- Market Size 2035 (USD million): 3,039.92
- CAGR 2026 to 2035: 14.0 %
- CAGR by Component: Electrical Infrastructure: 15.8 %
- CAGR by Facility Type: Power-Integrated Campuses: 17.2 %
- CAGR by End User: AI and GPU Cloud Operators: 19.4 %
- CAGR by Region: Southern District: 17.6 %
- Cap on Each New Data Center, October 2026 (Megawatts): 200
- Pending Grid Connection Requests, July 2026 (Megawatts): 27,000
- Market Share by Region 2025: Tel Aviv and Central District (Dominant Share)
Capacity is shifting from enterprise colocation towards large, artificial intelligence ready campuses leased to cloud and graphics processor operators, while grid limits decide where and how fast builders can deliver.
Key Trends in the Israel Hyperscale Data Center Market
The Israel hyperscale data center market is being reshaped by grid rationing, power-integrated campus plans and very large neocloud commitments.
1. October 2026 - Electricity Authority Outlines 200 MW Cap and 1,000 MW Allocation
- On 18 October 2026 the Electricity Authority published the main points of new grid-connection rules for large data centers.
- Developers must post NIS 2 million per requested megawatt, and facilities need mechanisms to disconnect during extreme demand.
- A three-week public consultation follows, so the final framework may still change before it takes effect.
- Dalia Energy said on 25 August 2026 it will hold half of a planned data center of up to 250 MW north of Ashdod port, with Serverfarm and the Israel Infrastructure Fund.
- Cost of the building and substation rose to USD 4.5 billion, and power would come from a nearby 850 MW gas plant.
- Direct connection is not yet legal, so the project depends on a pending regulatory change.
- On 20 July 2026 the Authority paused processing of applications of 8 MW or more, describing the freeze as an emergency brake.
- Noga reported roughly 19,000 MW of new requests in two months, on top of a backlog of about 8,000 MW.
- VisionWave dropped its plan for a hyperscale facility in Israel, citing the pause as a key factor.
- Crusoe agreed to lease about 57.6 MW at Idan HaNegev and 10 MW in Haifa from Mega DC, with delivery from the second quarter of 2027.
- The company has promised at least 45,000 Nvidia Vera Rubin processors for its Israeli halls.
- Capacity of about 150 MW within two years would overtake Nebius, reshaping the local tenant mix.
Regulators are rationing megawatts, developers are pairing campuses with dedicated gas supply, and neocloud tenants are signing long leases, which together favour well-funded builders over speculative applicants.
Recent Market Developments in the Israel Hyperscale Data Center Market
Recent developments, presented from the most recent, show Nvidia's expanding presence, Crusoe's entry, a large lease for Nebius and the first Nebius site in Modi'in.
1. July 2026 - Nvidia Opens Expanded Beersheva Research Centre
- Nvidia opened its enlarged Beersheva centre on 6 July 2026, about three times the size of its previous offices there.
- The company employs more than 6,000 people across five Israeli research centres, and it plans a Kiryat Tivon campus for up to 10,000 staff.
- Initial occupancy of Kiryat Tivon is planned for 2031, which keeps a strong customer anchoring Israeli cloud demand.
- Trade press reported on 28 April 2026 that Crusoe leased about 40 MW in a facility being built by Anan Group in Afula.
- The campus has since expanded to 80 MW and is targeting about 100 MW on a 200-dunam site.
- Mega Or also bought the Alliance tire factory site in Hadera for NIS 1 billion in April 2026.
- On 6 January 2026 Mega Or said its data center unit would supply Nebius with 80 MW at Masmiyya and Beit Shemesh.
- The investment is about USD 880 million, and deliveries run from the third quarter of 2026 to the first quarter of 2027.
- Mega DC expects about NIS 300 million of additional annual revenue from the contract.
- The Modi'in facility launched on 20 October 2025 with 8 MW and about 4,000 Nvidia graphics processors.
- A quarter of its capacity goes to the Israel Innovation Authority for the national supercomputer.
- The site proved the model that later 80 MW and 40 MW leases followed.
Nvidia's local expansion, new leases for graphics processor clouds and the first operating neocloud site show demand converting into contracted capacity rather than speculative plans.
Israel Hyperscale Data Center Industry Segmentation
The Expert Market Research’s report on the Israel Hyperscale Data Center Market offers a detailed analysis of the market based on the following segments.
Market Breakup by Component
- Electrical Infrastructure
- Mechanical and Cooling Infrastructure
- General Construction
- Colocation and Operating Services
- Others
Market Breakup by Facility Type
- Above-Ground Campuses
- Underground and Fortified Facilities
- Power-Integrated Campuses
- Others
Market Breakup by End User
- Cloud Service Providers and Hyperscalers
- AI and GPU Cloud Operators
- Government and Defense
- Enterprises and Others
- Others
Market Breakup by Region
- Tel Aviv and Central District
- Haifa and Northern District
- Jerusalem
- Southern District
- Others
CAGR 2026 to 2035, Market by Region
- Tel Aviv and Central District: 12.1 %
- Haifa and Northern District: 14.6 %
- Jerusalem: 15.3 %
- Southern District: 17.6 %
- Others (incl. Ashdod coast and Judea and Samaria): 13.2 %
Competition combines Israeli developers with listed property groups, global neocloud tenants and power-linked infrastructure funds. Entry barriers include grid allocation, land near substations, financial guarantees, security-driven design standards and the ability to commit billions of shekels before tenants pay.
Mega Or Holdings
Mega Or Holdings is an Israeli listed property group, controlled by Zahi Nahmias, whose Mega DC unit builds and leases large data centers. In January 2026 it contracted 80 MW to Nebius, and in June 2026 it agreed to lease about 67.6 MW to Crusoe at Idan HaNegev and in Haifa. Its Hadera site purchase for NIS 1 billion in April 2026 was later affected by the proposed 200 MW cap.
Nebius Group
Nebius Group, headquartered in Amsterdam, the Netherlands, is a graphics processor cloud operator that supplies artificial intelligence training and inference capacity. In October 2025 it launched an 8 MW site with Mega Or at Modi'in using about 4,000 Nvidia processors, and in January 2026 it signed for 80 MW more. A quarter of the Modi'in capacity supports the Israel Innovation Authority's national supercomputer.
Crusoe
Crusoe, headquartered in Denver, Colorado, builds and operates artificial intelligence cloud infrastructure. In April 2026 it leased about 40 MW from Anan Group in Afula, and by June 2026 it had signed for about 67.6 MW more from Mega DC and announced about USD 10 billion of Israeli investment over 10 to 15 years. It has promised at least 45,000 Nvidia Vera Rubin processors for its Israeli facilities.
MedOne
MedOne is an Israeli data center operator offering colocation, interconnection and cloud services from underground facilities in Tel Aviv, Petah Tikva, Tirat HaCarmel and Ramla. Its new Kfar Yona campus has two underground data centers across about 30,000 square metres, an investment above NIS 1 billion, with the first opening during 2026 and the second in 2027. Its company site lists further sites, including Dimona, in the pipeline.
Other players operating in the Israel hyperscale data center market include NVIDIA, Anan Group, Keystone Infrastructure Fund, Dalia Energy, and EdgeConneX, alongside Serverfarm, cloud platform operators, construction contractors, electrical equipment suppliers and independent colocation providers serving hyperscale and AI tenants across Israel.
Key Insight
Competition rests on securing grid allocation, land near power sources and long-term tenants, while new guarantees and size caps favour financially strong developers over speculative applicants.
Frequently Asked Questions: Israel Hyperscale Data Center Market
What is the size of the Israel hyperscale data center market in 2025?
The Israel hyperscale data center market is valued at USD 820.00 million in 2025, supported by neocloud leases, the national artificial intelligence plan and rising cloud demand, with Tel Aviv and the Central District as the largest region.
What is the forecast for the Israel hyperscale data center market by 2035?
The market is forecast to reach USD 3.03 billion by 2035, growing at a CAGR of 14.0 % over the 2026 to 2035 period, driven by artificial intelligence leases, new gas-linked campuses and large operator investments, partly offset by regulatory limits on grid access.
Which component has the highest CAGR in the Israel hyperscale data center market?
Electrical Infrastructure records the highest CAGR at an estimated 15.8% through 2035, as substations, backup power and grid connections determine which campuses can be energised.
Which region dominates the Israel hyperscale data center market?
Tel Aviv and the Central District dominate, owing to metropolitan interconnection hubs and sites such as Modi'in and Kfar Yona. The Southern District is the fastest-growing region at an estimated 17.6% CAGR.
Who are the key players in the Israel hyperscale data center market?
Key players include Mega Or Holdings, Nebius Group, Crusoe, MedOne, NVIDIA, Anan Group, Keystone Infrastructure Fund, Dalia Energy, and EdgeConneX.
What is the Electricity Authority's cap on new data centers?
In October 2026 the Electricity Authority outlined a limit of 200 MW of consumption for each new data center, with 1,000 MW allocated to large projects and 300 MW kept for government and defence needs.
Why did Israel freeze new data center grid applications in 2026?
Requests reached about 27,000 MW, roughly three times average national consumption. On 20 July 2026 the Electricity Authority paused applications of 8 MW or more for 140 days to design an allocation policy.