In 2025, the market is valued at USD 485.00 million and is forecast to grow at a CAGR of 9.0%, reaching USD 1.14 billion by 2035. Growth is driven by Dutch IT capacity passing 1.5 GW at the end of 2025, a planned rise to 2.8 GW by 2031, and the need to build power systems that can work around a congested national grid.
Market Overview
The Netherlands data center power market is expanding under constraint rather than in free flight. Demand for protected power keeps rising with cloud and AI workloads, yet the high-voltage grid around Amsterdam and Schiphol is full, so buyers turn to batteries, flexible connections, prefabricated modules and equipment replacement.
Three forces are shaping the market: capacity growth, with Dutch IT capacity up 7% to just over 1.5 GW in 2025; grid congestion, with permit processing near 4.5 years and connection waits of up to ten years; and resilience, after a fire in the power supply of a data center in Almere stopped services nationwide in May 2026.
In September 2025 Stedin ordered 60 MW of mtu gas gensets from Rolls-Royce to ease grid bottlenecks, in April 2026 a court backed TenneT in pausing a 70 MW connection at Vijfhuizen, and in July 2026 Noord-Holland forecast 92 data centers by 2035.
Key Market Trends and Insights
- Rapid capacity growth: The Dutch Data Center Association reported in June 2026 that IT capacity rose 7% to just over 1.5 GW in 2025, the base on which power equipment demand rests.
- Growth path to 2031: The same association expects about 12% annual growth to 2.8 GW by 2031, with a restrictive case of 2.1 GW if power and permits stay scarce.
- Congested high-voltage grid: A court in Arnhem ruled in April 2026 that the Vijfhuizen grid is at full capacity, leaving Goodman's 70 MW request on a waiting list.
- Resilience under scrutiny: The 7 May 2026 fire in the power supply of NorthC's Almere site took Statistics Netherlands and Utrecht University offline for hours.
The market is moving from conventional site-built power rooms towards modular, battery-backed and grid-interactive designs. UPS systems lead in value because every hall needs conditioned power, while batteries and energy storage advance fastest as operators seek flexible connections. Colocation remains the largest buyer, and hyperscale and cloud projects grow quickest where designated zones allow large sites. North Holland remains the largest region, and Groningen grows quickest as Eemshaven draws large campuses. Gas-fired backup, heat reuse, prefabricated modules and tighter fire safety point to a durable change in how Dutch data center power is specified, even as permits and transformer lead times pace the build-out.
Key Metrics
- Market Size 2025: USD 485.00 million
- Projected Market Size 2035: USD 1.14 billion
- CAGR 2026 to 2035: 9.0%
- Fastest-Growing Power Equipment Type: Batteries and Energy Storage: 12.6% CAGR
- Fastest-Growing Data Center Type: Hyperscale and Cloud: 11.2% CAGR
- Largest Revenue Segment 2025: UPS Systems
- Dominant Region: North Holland (Amsterdam)
- Highest CAGR by Region: Groningen: 11.4%
- Dutch data center IT capacity, end of 2025: Just over 1.5 GW
- Base Market Amount 2025: USD 485.00 million
Capacity Growth Meets a Congested Grid
Revenue is on course to expand by about 137% across the decade, from USD 485.00 million in 2025 to USD 1.14 billion in 2035 at a 9.0% CAGR. IT capacity is expected to reach 2.8 GW by 2031, yet TenneT warns that constraints around Schiphol could last until about 2035.
Storage and Modular Designs Lead Growth
UPS Systems hold the largest share, but Batteries and Energy Storage grows at an estimated 12.6% CAGR and Prefabricated Power Modules at an estimated 11.8% CAGR through 2035. Flexible grid connections and long permit times favor equipment that can be delivered quickly and relocated.
Resilience and Heat Reuse Reshape Specifications
The Almere fire and new heat networks show that power rooms now carry safety, grid and community expectations beyond uptime. Buyers are asking for segregation, metering and flexibility alongside capacity.
- NorthC's Almere power supply burned on 7 May 2026 and was shut off at the fire department's request
- Switch Datacenters signed a heat agreement in Uithoorn in July 2026 backed by an SDE++ subsidy
- Stedin's 60 MW of mtu gas gensets is designed for relocation until 2036
- Base Year: 2025
- Historical Period: 2019 to 2025
- Forecast Period: 2026 to 2035
- Market Size 2025 (USD million): 485.00
- Market Size 2035 (USD million): 1,148.18
- CAGR 2026 to 2035: 9.0 %
- CAGR by Power Equipment Type: Batteries and Energy Storage: 12.6 %
- CAGR by Data Center Type: Hyperscale and Cloud: 11.2 %
- CAGR by Delivery Model: Prefabricated Power Modules: 11.8 %
- CAGR by Region: Groningen: 11.4 %
- Dutch Data Center IT Capacity 2025 (Gigawatt): 1.50
- Stedin mtu Gas Genset Capacity (Megawatt): 60.00
- Market Share by Region 2025: North Holland (Amsterdam) (Dominant Share)
Demand is shifting towards batteries, modular power rooms and flexible connections as the grid stays congested, while colocation keeps volumes broad. North Holland leads, and Groningen grows fastest.
Key Trends in the Netherlands Data Center Power Market
The Netherlands data center power market is being reshaped by rising site power requests, long equipment lead times, heat reuse agreements and growing hyperscale activity.
1. September 2026 - Single-Site Power Requests Reach 300 MW as Transformer Lead Times Stretch
- Trade press reported on 21 September 2026 that single-site requests once at 30 MW to 60 MW can now reach 300 MW.
- Transformer lead times can extend up to three years, according to market participants quoted in the same coverage.
- Long lead times favor suppliers with local stock, European factory capacity and prefabricated designs.
- The municipality of Uithoorn signed an agreement in July 2026 for Switch Datacenters to supply residual heat to growers in De Kwakel-Kudelstaart.
- The national government granted an SDE++ subsidy, and Liander found greenhouse electrification would be very difficult without the link.
- The site is to run on Dutch wind and solar power, tying power systems to heat metering.
- The association reported on 9 June 2026 that permit processing takes about 4.5 years and grid connection waits can reach ten years.
- It proposed flexible connections, battery storage, congestion management and Dutch Data and Energy Clusters to unlock capacity.
- Flexible connections raise demand for batteries and fast-switching equipment inside facilities.
- The Dutch Data Center Association said on 30 March 2026 that at least seven hyperscale projects are proceeding, four of them in Haarlemmermeer.
- Data centers use about 5% of national electricity, and grid operators expect that share to double in the coming years.
- A House motion to curb hyperscale growth passed, but permits are largely granted, so equipment orders can follow.
Larger site requests, long transformer lead times, heat reuse and flexible connections are the main structural forces, while permit delays and grid waiting lists remain the main risk to volume.
Recent Market Developments in the Netherlands Data Center Power Market
Recent developments, presented from the most recent, show provincial growth forecasts, a power room fire, a court ruling on grid capacity and gas generator deployment by a grid operator.
1. July 2026 - Noord-Holland Forecasts 92 Data Centers by 2035
- The province said on 6 July 2026 that it hosted 67 data centers in 2025 and expects 83 by 2030 and 92 by 2035.
- Most new projects are expected in Hollands Kroon, Haarlemmermeer and Amsterdam, and new sites will face strict conditions.
- Deputy Esther Rommel said the grid is already under pressure from congestion and needs expansion.
- The fire started in a technical room at about 8:40 a.m. on 7 May 2026 and was under control about 12 hours later.
- Part of the power supply burned, and the power was switched off at the fire department's request, halting hosted systems.
- Statistics Netherlands, Utrecht University and Transdev were affected, which puts power room fire safety on operator agendas.
- The Arnhem court ruled on 29 April 2026 that the regional grid near Schiphol is genuinely at full capacity.
- Goodman sought a 70 MW connection and had argued it should be exempt from the waiting list, which the court rejected.
- TenneT said capacity constraints could last until around 2035, favoring on-site storage and generation.
- On 23 September 2025 Rolls-Royce announced 24 containerized mtu gas gensets, grouped in six 10 MW units, for Stedin in the province of Utrecht.
- Flexpowernet will operate the units to ease grid bottlenecks of up to 250 MW, and they are intended for use until 2036.
- The package includes a ten-year availability guarantee and relocation within the Netherlands.
Provincial growth plans, a power room fire, a court ruling on grid capacity and gas generator deployment show buyers prioritising resilience and self-supplied flexibility through the forecast period.
Netherlands Data Center Power Industry Segmentation
The Expert Market Research’s report on the Netherlands Data Center Power Market offers a detailed analysis of the market based on the following segments.
Market Breakup by Power Equipment Type
- UPS Systems
- Generators and Engines
- Switchgear and Power Distribution
- Batteries and Energy Storage
- Others
Market Breakup by Data Center Type
- Colocation
- Hyperscale and Cloud
- Enterprise and Government
- Edge
- Others
Market Breakup by Delivery Model
- Site-Built Systems
- Prefabricated Power Modules
- Retrofit and Upgrade
- Service and Maintenance
- Others
Market Breakup by Region
- North Holland (Amsterdam)
- South Holland
- Flevoland
- North Brabant and Limburg
- Groningen
- Others
CAGR 2026 to 2035, Market by Region
- North Holland (Amsterdam): 7.9 %
- South Holland: 9.2 %
- Flevoland: 9.8 %
- North Brabant and Limburg: 9.5 %
- Groningen: 11.4 %
- Others (incl. Utrecht, Gelderland, Overijssel, Drenthe, Friesland and Zeeland): 8.6 %
Competition combines global electrical majors, engine makers and regional installers. Entry barriers include factory capacity, local stock, certification, framework agreements with large operators, service coverage and the ability to deliver within long transformer and grid-connection lead times.
Schneider Electric
Schneider Electric, headquartered in Rueil-Malmaison, France, supplies UPS systems, switchgear, busway, power distribution and monitoring software to colocation and cloud operators, including Dutch sites. On 30 April 2026 it reported record first-quarter revenue of EUR 9.8 billion, up 4.7%, with data center and network demand growing at double-digit rates. Its breadth across the power chain suits prefabricated power modules for new Dutch halls.
Vertiv
Vertiv, headquartered in Westerville, Ohio, supplies UPS systems, switchgear, busway, batteries and thermal products for data centers worldwide, including Europe. On 3 March 2026 it announced a double-stack PowerBar Track busway rated up to 2,500 A under IEC 61439-6. On 29 July 2026 it reported second-quarter net sales of USD 3.27 billion, up 24%, while EMEA sales fell 2.4% organically.
Eaton
Eaton, headquartered in Dublin, Ireland, supplies UPS systems, switchgear, power distribution and energy storage to data center operators, including in Europe. On 31 July 2026 it reported record second-quarter revenue of USD 8.5 billion, up 21%, with revenue in Europe and Asia-Pacific up about 20%, and raised full-year organic growth guidance to 11% to 13%. Its storage-capable UPS range suits Dutch operators seeking flexible grid connections.
Rolls-Royce
Rolls-Royce supplies mtu diesel and gas generator sets for data center backup through its power systems business in Friedrichshafen, Germany. On 23 September 2025 it announced that Stedin will use 24 containerized mtu gas gensets, six 10 MW units totaling 60 MW, in the province of Utrecht to ease grid bottlenecks until 2036. The contract covers engineering, construction, maintenance and a ten-year availability guarantee, with Flexpowernet operating the units.
Other players operating in the Netherlands data center power market include ABB, Siemens, Legrand, Cummins, and Caterpillar, alongside regional electrical installers, generator distributors, battery integrators, prefabricated module builders and service contractors supplying power systems to colocation, hyperscale, enterprise and edge sites across the Netherlands.
Key Insight
Competition rests on factory capacity, local stock, certification and service coverage rather than price alone, while long transformer lead times favor suppliers able to deliver modular, storage-ready systems quickly.
Frequently Asked Questions: Netherlands Data Center Power Market
What is the size of the Netherlands data center power market in 2025?
The Netherlands data center power market is valued at USD 485.00 million in 2025, supported by IT capacity above 1.5 GW, a planned rise to 2.8 GW, tougher grid access and a growing role for batteries and modular power systems, with North Holland as the largest region.
What is the forecast for the Netherlands data center power market by 2035?
The market is forecast to reach USD 1.14 billion by 2035, growing at a CAGR of 9.0 % over the 2026 to 2035 period, driven by hyperscale projects, grid congestion that favors on-site storage and flexibility, heat reuse agreements and greater attention to power room resilience.
Which power equipment type has the highest CAGR in the Netherlands data center power market?
Batteries and Energy Storage records the highest CAGR at an estimated 12.6% through 2035, as flexible grid connections, congestion management and backup requirements raise demand for on-site storage.
Which region dominates the Netherlands data center power market?
North Holland (Amsterdam) dominates, as Amsterdam, Haarlemmermeer and Hollands Kroon host the largest cluster of sites. Groningen is the fastest-growing region at an estimated 11.4% CAGR, helped by the Eemshaven hyperscale zone.
Who are the key players in the Netherlands data center power market?
Key players include Schneider Electric, Vertiv, Eaton, Rolls-Royce, ABB, Siemens, Legrand, Cummins, and Caterpillar.
What is a UPS system in a data center?
An uninterruptible power supply conditions incoming power and bridges the gap until generators start, using batteries to keep servers running. It is the largest equipment category in Dutch data center power systems.
What is grid congestion and how does it affect Dutch data centers?
Grid congestion means the network has no spare capacity for new connections. An Arnhem court ruled in April 2026 that the Vijfhuizen grid was full, so operators use batteries, gensets and flexible connections.